Issue #4011: Greška u skladištenju
Issue #4117: Problem potrprojekta
Issue #4120: Kontrola datuma i čišćenje preparata sa isteklim rokom trajanja
Issue #4122: Kontrola datumka u magacinu
 
49
50
51
52
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
 
 
 
Apoteka
 
 
 
 
 
Verzija 1.1. 100%
 
 
 
New 100%
Issue #4011: Greška u skladištenju

Project: Apoteka
Status: New
Start date: 12/07/2025
Due date: 12/10/2025
Assignee: Svetlana Trifković
Priority: High
 
 
 
Farm.tehničari
 
 
 
 
New 0%
Issue #4120: Kontrola datuma i čišćenje preparata sa isteklim rokom trajanja

Project: Farm.tehničari
Status: New
Start date: 12/15/2025
Due date: 12/20/2025
Assignee: Aleksa Vidakovic
Priority: Normal
 
 
New 0%
Issue #4122: Kontrola datumka u magacinu

Project: Farm.tehničari
Status: New
Start date: 12/15/2025
Due date: 12/20/2025
Assignee: Svetlana Trifković
Priority: Normal
 